Construction DB | Construction Site Handbook | Cost Budget

Construction Site Handbook

Share your expertise and experience with the Construction DB community. You are free to add or edit any of the articles in the Construction Knowledge Collaboration Project.

[English | 简体] Cost Budget

A budget for expenditures on deployed plant , labour , materials , site supervision , office overhead , temporary works , temporary diversions , permits and licenses , suppliers , sub-contractors , safety , environmental protection , financial charges and insurances should be well prepared for guidance of the project cost . The budget for a new project could be forecast based on the past job(s) of similar nature , with cost data to be adjusted to bring the cost to an updated value . The general issues are as follows : -

a) Purchased Plant : plant cost , maintenance , fuel , mobilization , plant operator and storage area .
b) Hired Plant : availability , hire rate , hired period , fuel , mobilization and de-mobilization .
c) Labour : directly employed , sublet by daywork , overtime work , shift work , various trades , and numbers required at high / low seasons .
d) Materials : material cost , delivery lead time , shipping cost , customs , storage area , internal transportation , wastage and disposal .
e) Site Supervision : directly employed , sublet by package , shift work and size required at high / low seasons .
f) Office Overhead : size required at commencement , during execution and after completion of works .
g) Temporary Works : timber-made , steel-made , pre-fabricated , by erection and dismantling , ICE certifications for work , to be re-used , make good works , transportation , storage area and disposal .
h) Temporary Diversions : utility diversion , road diversion , signages and barriers , Temporary Traffic Management Scheme ( TTMS ) and reinstatement .
i) Licenses and Permits : application fees .
j) Suppliers : minimum order quantity ( MOQ ) , downpayment , schedule of shipments and follow-up payment terms .
k) Sub-contractors : lump sum price , on re-measurement basis , advance payment , retention money , schedule of payments and final account .
l) Safety : complying with the contract requirements , tool box talks , safety promotion , signage , labels and safety audits .
m) Environmental Protection : complying with the contract documents , measuring equipments , cost of tests and reinstatement .
n) Financial Charges : bank bond , interests , taxation and inflation .
o) Insurances : Contractor’s All Risks ( CAR ) , plant insurance and Employee’s Compensation Scheme .

Running Cost
After preparation of the budget with itemized costs , an expenditure schedule of running costs on the basis of contract period and programmed works should be listed out for financial evaluation . This is a good time to re-assess whether some other part of the works should be subcontracted instead of executing by direct labour in order to alleviate the financial burden at the peak time .

Cost Centres
This is a kind of payment terms that lays out a series of fixed payments ( partial payments of the contract sum ) to be certified at various status of completion of works as required by the Contract . The works that require to be completed may be part of the permanent works , or provision of temporary work , or approval of the trial erection , or receipt of the major material on site , etc .
In this case , the estimator is quite easily to predict the forthcoming income if the programmed works are being executed on time . In some cases , the re-scheduling of programmed works might help to achieve these cost centres earlier in order to release the financial burden of the running cost .


Cost Budget Sub-Pages