Construction DB | Construction Site Handbook | Milestones and Forecasts

Construction Site Handbook

Share your expertise and experience with the Construction DB community. You are free to add or edit any of the articles in the Construction Knowledge Collaboration Project.

[English | 简体] Milestones and Forecasts

Milestones
This is a series of check points that are required by the Contract to determine the partial completion or substantial completion of the major work at intermittent time during the contract period . It lays out the extent of works required to be completed at a certain time interval ( with a key date ) after commencement of work in order to govern the programme and progress of the project .

In case there is any variation work instructed by the Engineer that interrupts the works progress of the critical activities to achieve these milestones , an application for extension of time ( EOT ) may be required ; or the Engineer should issue instruction to accelerate the affected works should he still wish to maintain the milestone works at the specified key date ( KD ) .

Cash Flow Forecast
Movements of cash either into or out of the project account are all regarded as cash flows . With reference of the above running costs schedule , cost centres and milestones , the estimator could then prepare a cash flow forecast on the basis of probable incomes ( valuation of workdone ) , retention money and predicted expenditures in accordance with the works programme . This forecast will help the commercial staff to determine the amount and time that are required for financial supports .

Fluctuation
Fluctuations are the changes in the price of wages and materials during the period of construction and are based on the monthly publication of “ Index of Wage Rates ” for the building industry by the Census and Statistics Department of the Hong Kong Government . These indices of wage rates are evaluated and averaged from the preceding 3 months wages return submitted by the main contractors of prevailing major projects in Hong Kong .

If the percentage of increase / decrease is less than 10% , no adjustment will be made to the contract sum ; but if the percentage of increase / decrease is more than 10% , the contract sum will then be adjusted by the net amount that exceeds 10% .

Previously most contracts , particularly for large sized project , are having a clause for fluctuations . However nowadays , the employer would rather shift the risk of wages and materials fluctuations to the contractor to consider at the tendering stage and remove this clause from the contract documents .

Auditing
For a large sized project , there are so many trades of works to be dealt with . Every issue existing on a construction site will affect the profit and loss of a contract , no matter it is huge or tiny . For instance the drinking water for the workers , it is crystal clear that the cost of provision of soft drinks is higher than bottled mineral water , in turn is higher than the bulk mineral water and in turn is higher than the boiled tap water being cooled overnight .

Thus , internal audits or independent audits are essential to keep the works and progress ( technical audit ) , the incomes and expenditures ( financial audit ) and the safety issues ( safety audit ) in good order and in an efficient manner . The sophisticated review of these audits will surely help to complete the project economically and efficiently .

Project Bonus / Penalty
For commercial projects , sometimes there is an offer of bonus stated in the contract if the whole of project is completed on time or earlier than the target date . This bonus clause may encourage the contractor to keep a close eye on the progress and coordination of the works , and even could make use of this clause to voluntarily accelerate the works to achieve an early completion should the contractor finds beneficial and profitable . On the other hand , the penalty clause is being used to push the contractor to finish the works on time .

Nowadays , these bonus / penalty clauses are also commonly applying to the safety issues on a construction site by which to encourage the main contractor to keep the site in a safe manner and without or with low accident frequency .


Milestones and Forecasts Sub-Pages