[English | 简体] Construction Quality Plan ( CQP )
For some large sized projects with major amount of repetitive work like the railway , tunnel , launching of viaduct segments or a series of residential buildings , the Engineer may request the contractor to submit a CQP for discussion . Since these projects are usually executed in phrases of work or commence work simultaneously at various locations , a well planned CQP will help the Engineer to have full knowledge of how the project could be completed in compliance with the specifications and drawings and most important of all , finishing at the same time with full scale .
The CQP shall state at least the followings for consideration : -
a) Programme , phrases and shifts of work ;
b) Resources like supervision , labour , plant and materials ;
c) Facilities like communication , transport , vertical delivery , temporary water and power supply ;
d) Utilities diversions , road diversions and TTMS ;
e) Manufacturing , storage and delivery of precast / pre-fabricated items ;
f) Design , erection , dismantling and location of temporary work / plant ;
g) Method statements and sequence of works ;
h) Construction process and QA / QC / NCR systems ;
g) Identification , labeling and protection of work before handover ;
h) Inspection and Testing Plan ( ITP ) ;
i) Handover Plan .