Construction DB | Construction Site Handbook | Cover metre test

Construction Site Handbook

Share your expertise and experience with the Construction DB community. You are free to add or edit any of the articles in the Construction Knowledge Collaboration Project.

[English | 简体] Cover metre test

Concrete cover to the steel bars inside a concrete pour is critical to the durability of reinforcement for the structure . Once the Engineer is in doubt , it may require to conduct a Cover Metre Test to verify the as-cast concrete cover to the reinforcement to see whether the condition is acceptable . During casting , the concrete cover is usually maintained by the insertion of cover blocks ( usually made of concrete , epoxy or plastic ) between the formwork and steel bars . However owing to some cases occur , the cover to steel bars might be found less than specified limit during or after the concrete pour . The situations are usually as follows : -

1. The space between the formwork and steel bar is less than the size of cover block such that the cover block sheared after force insertion .
2. The cover blocks are disturbed by the internal vibrator that is working too close and displaces the blocks from its original position .
3. The movement of reinforcement cage might occur during concreting .


Cover metre test Sub-Pages