Air Test

Are you a Construction Professional? Can you add any information to this article? Take one minute to join up and start editing, ask a question or post a new article

This test will be set up and conducted by site supervisor and the procedures in brief are as follows : -

1. Before test , the ends of the pipeline are plugged using expanding disc stoppers and one end is connected with a U-tube manometer .
2. Air to be pumped into the pipeline until a test pressure of slightly more than 100mm of water is observed in the U-tube .
3. Allow a few minutes for stabilization of the ambient temperature , then adjust the air pressure to 100mm of water in the U-tube . Lock the device without further pumping .
4. After five-minute test period , read the pressure in the U-tube and record .
5. It is satisfactory if the air pressure remains above 75mm head of water at the end of the air test .

Disclaimer; This wiki article is contributed by our members without formal peer review and should not be taken as legal or contractual advice. All information read here is without any implied warranty of fitness for any purpose or use whatsoever. Even articles that have been vetted by informal review may later have been edited inappropriately, just before you view them.