For large sized projects with major amounts of repetitive work like the railway , tunnel , launching of viaduct segments or a series of residential buildings , the Engineer may request the contractor to submit a CQP for discussion . Since these projects are usually executed in phrases of work or commence work simultaneously at various locations , a well planned CQP will help the Engineer to have full knowledge of how the project could be completed in compliance with the specifications and drawings and most important of all , finishing at the same time with full scale .
The CQP shall state at least the followings for consideration : -
a) Programme , phrases and shifts of work ;
b) Resources like supervision , labour , plant and materials ;
c) Facilities like communication , transport , vertical delivery , temporary water and power supply ;
d) Utilities diversions , road diversions and TTMS ;
e) Manufacturing , storage and delivery of precast / pre-fabricated items ;
f) Design , erection , dismantling and location of temporary work / plant ;
g) Method statements and sequence of works ;
h) Construction process and QA / QC / NCR systems ;
g) Identification , labeling and protection of work before handover ;
h) Inspection and Testing Plan ( ITP ) ;
i) Handover Plan .
Disclaimer; This wiki article is contributed by our members without formal peer review and should not be taken as legal or contractual advice. All information read here is without any implied warranty of fitness for any purpose or use whatsoever. Even articles that have been vetted by informal review may later have been edited inappropriately, just before you view them.