Ideally , all the details of works and particular notes should be quoted on the construction drawings at the tender stage or at least at commencement of works , however it rarely can be achieved . Sometimes the full set of construction drawings are even not yet finished at time of awarding the contract . Thus the Engineer / Architect will usually issue a series of working drawings during the construction period or amend and supplement details to the tender drawings from time to time for construction .
While the contract price is based on the bills of quantities taking off from the tender drawings , this practice may incur additional or variation work to the contractor and subsequently affects the works programme and progress . In view of this situation , a detailed drawings register must be kept and maintained for commercial purpose .
The drawings register should include at least the followings : -
a) Date and time of receipt ;
b) Drawing number ;
c) Revision number ;
d) Drawing title ;
e) Purposes of Issue eg. for construction , for information or for tender ;
f) Accompany document reference eg. Site Instruction ( SI ) , Drawing Amendment Notification ( DAN ) , Variation Order ( VO ), transmittal , correspondence , etc.
After the award of contract , the Engineer will issue construction or working drawings via its site representative to the contractor for execution of work . These construction drawings at receipt should be well dated and documented . A log book and a standard chop should be prepared for onward registration . The key personnel should try to explore any interface problems between the adjacent main contract and inform the Engineer for solution if applicable . Copies of these received drawings are then prepared for in-house allocation and sub-contract purposes . Further receipt of drawing revisions shall be updated , registered and maintained in a traceable manner for reference .
It is recommended that every drawing and sketch received to be registered with date and transmittal reference. This data is often critical for tracing back any design related delays or disruptions.
Disclaimer; This wiki article is contributed by our members without formal peer review and should not be taken as legal or contractual advice. All information read here is without any implied warranty of fitness for any purpose or use whatsoever. Even articles that have been vetted by informal review may later have been edited inappropriately, just before you view them.