Waterproofing structures may be required to test for watertightness after completion of work . The test is to apply static pressure by means of ponding water on the internal face and no head of water on the external face . Testing period may vary from 24 hours to 3 days as required by the Specification . Site supervisor should record any leaks or damp patches and submit to the Engineer for assessment .

Disclaimer; This wiki article is contributed by our members without formal peer review and should not be taken as legal or contractual advice. All information read here is without any implied warranty of fitness for any purpose or use whatsoever. Even articles that have been vetted by informal review may later have been edited inappropriately, just before you view them.