A budget for expenditures on deployed plant , labour , materials , site supervision , office overhead , temporary works , temporary diversions , permits and licenses , suppliers , sub-contractors , safety , environmental protection , financial charges and insurances should be well prepared for guidance of the project cost . The budget for a new project could be forecast based on the past job(s) of similar nature , with cost data to be adjusted to bring the cost to an updated value . The general issues are as follows : -
a) Purchased Plant : plant cost , maintenance , fuel , mobilization , plant operator and storage area .
b) Hired Plant : availability , hire rate , hired period , fuel , mobilization and de-mobilization .
c) Labour : directly employed , sublet by daywork , overtime work , shift work , various trades , and numbers required at high / low seasons .
d) Materials : material cost , delivery lead time , shipping cost , customs , storage area , internal transportation , wastage and disposal .
e) Site Supervision : directly employed , sublet by package , shift work and size required at high / low seasons .
f) Office Overhead : size required at commencement , during execution and after completion of works .
g) Temporary Works : timber-made , steel-made , pre-fabricated , by erection and dismantling , ICE certifications for work , to be re-used , make good works , transportation , storage area and disposal .
h) Temporary Diversions : utility diversion , road diversion , signages and barriers , Temporary Traffic Management Scheme ( TTMS ) and reinstatement .
i) Licenses and Permits : application fees .
j) Suppliers : minimum order quantity ( MOQ ) , downpayment , schedule of shipments and follow-up payment terms .
k) Sub-contractors : lump sum price , on re-measurement basis , advance payment , retention money , schedule of payments and final account .
l) Safety : complying with the contract requirements , tool box talks , safety promotion , signage , labels and safety audits .
m) Environmental Protection : complying with the contract documents , measuring equipments , cost of tests and reinstatement .
n) Financial Charges : bank bond , interests , taxation and inflation .
o) Insurances : Contractor’s All Risks ( CAR ) , plant insurance and Employee’s Compensation Scheme .
Running Cost
After preparation of the budget with itemized costs , an expenditure schedule of running costs on the basis of contract period and programmed works should be listed out for financial evaluation . This is a good time to re-assess whether some other part of the works should be subcontracted instead of executing by direct labour in order to alleviate the financial burden at the peak time .
Cost Centres
This is a kind of payment terms that lays out a series of fixed payments ( partial payments of the contract sum ) to be certified at various status of completion of works as required by the Contract . The works that require to be completed may be part of the permanent works , or provision of temporary work , or approval of the trial erection , or receipt of the major material on site , etc .
In this case , the estimator is quite easily to predict the forthcoming income if the programmed works are being executed on time . In some cases , the re-scheduling of programmed works might help to achieve these cost centres earlier in order to release the financial burden of the running cost .
Cash Flow Forecast
Movements of cash either into or out of the project account are all regarded as cash flows . With reference of the above running costs schedule , cost centres and milestones , the estimator could then prepare a cash flow forecast on the basis of probable incomes ( valuation of workdone ) , retention money and predicted expenditures in accordance with the works programme . This forecast will help the commercial staff to determine the amount and time that are required for financial supports .
Fluctuation
Fluctuations are the changes in the price of wages and materials during the period of construction and are based on the monthly publication of “ Index of Wage Rates ” for the building industry by the Census and Statistics Department of the Hong Kong Government . These indices of wage rates are evaluated and averaged from the preceding 3 months wages return submitted by the main contractors of prevailing major projects in Hong Kong .
If the percentage of increase / decrease is less than 10% , no adjustment will be made to the contract sum ; but if the percentage of increase / decrease is more than 10% , the contract sum will then be adjusted by the net amount that exceeds 10% .
Previously most contracts , particularly for large sized project , are having a clause for fluctuations . However nowadays , the employer would rather shift the risk of wages and materials fluctuations to the contractor to consider at the tendering stage and remove this clause from the contract documents .
Auditing
For a large sized project , there are so many trades of works to be dealt with . Every issue existing on a construction site will affect the profit and loss of a contract , no matter it is huge or tiny . For instance the drinking water for the workers , it is crystal clear that the cost of provision of soft drinks is higher than bottled mineral water , in turn is higher than the bulk mineral water and in turn is higher than the boiled tap water being cooled overnight .
Thus , internal audits or independent audits are essential to keep the works and progress ( technical audit ) , the incomes and expenditures ( financial audit ) and the safety issues ( safety audit ) in good order and in an efficient manner . The sophisticated review of these audits will surely help to complete the project economically and efficiently .
Project Bonus / Penalty
For commercial projects , sometimes there is an offer of bonus stated in the contract if the whole of project is completed on time or earlier than the target date . This bonus clause may encourage the contractor to keep a close eye on the progress and coordination of the works , and even could make use of this clause to voluntarily accelerate the works to achieve an early completion should the contractor finds beneficial and profitable . On the other hand , the penalty clause is being used to push the contractor to finish the works on time .
Nowadays , these bonus / penalty clauses are also commonly applying to the safety issues on a construction site by which to encourage the main contractor to keep the site in a safe manner and without or with low accident frequency .
Disclaimer; This wiki article is contributed by our members without formal peer review and should not be taken as legal or contractual advice. All information read here is without any implied warranty of fitness for any purpose or use whatsoever. Even articles that have been vetted by informal review may later have been edited inappropriately, just before you view them.